In Cond Contract settlement process need to consider POs with PGI date GT settlement date

Experts,

Have a requirment inĀ Settlement Management.

Current process:In condition contract settlement process via tcode WB2R_SV, currently system considers only the POs of the same condition contract whose PGI date is within the settlement date.

Expected :The system should also allow to settle all the POs in that condition contract eventhough POs – PGI date is greater than settlement date.

Tried few BADIs with WB2_CC* but no luck. would be helpful if someone faced/implemented similar requirment.