Loading Time by Crane to be displayed on Order confirmation and Delivery confirmation (outbound)

Dear All,

I have one requirement received as below:

Customer wants loading done by Crane for material  to be included exactly with Time and agreed Rate on delivery note copy and order confirmation.

Currently on delivery note it is appeared as below:

Material No                      QTY Unit      Unit price     Unit       Net price USD
AB23000BW                    10 TO(ton)       35              1 TO      350
special Crane of 40M

Customer suggests  now as below. The query is how can we achieve this technically without ABAP code :

The suggestion would now be that the recorded tonnage is multiplied by a fixed value of 10 minutes and displayed either as text or as an additional item number, e.g.: “The included unloading time is XX minutes” or as a separate item number “Included unloading time”.

Item number also they need to be appeared automatically as soon as they select “Crane loading” in Delivery creation.

Thank you for the help.

Regards

SAPSCM