Hi Pros,
I’m looking for a way how can we manage the master data migration cycles in Public Cloud environment in an implementation project. During migration we have more steps what can be done in different tenants:
– functional and development test – can be done in starter tenant with limited data
– test with real life data – can be done in test tenant with limited data
– full migration test with real life data – can be done in test tenant once but how should we repeat it if there is any issue with any master data? Can we have somehow a new tenant where the full migration test can be repeated?
Also before a UAT takes place we should provide to our client a tenant where exactly the same data can be found what they will meet with in productive tenant, the reason behind is that on this way we can ensure our client the productive system will work on the same way as the tenant where they execute the UAT. However since every dummy data is in test tenant does not seem for us a reasonable way to perform the UAT there.
Waiting for any useful comment on this issue.